Muscat City Centre Hypermarket relies on Aggreko
The challenge for the customer
Muscat City Centre Hypermarket
needed up to four MW of reliable electrical power delivered at 11
kV. Without this, commissioning electrical and mechanical
systems would be incomplete.
Aggreko’s solution
Aggreko has specialist experience
gained by providing generating capacity to Carrefour in their Amjan
and Doha megastore projects. This meant we speedily provided
a dependable power package that operated continuously for four
weeks.
The benefits to the customer
The construction team was able to
commission and test all the systems satisfactorily.
Essential services such as air-conditioning were guaranteed to be
fully functioning when the retail centre opened for business.